Management
Plan
|
1 PROJECT
IDENTIFICATION
This Project Management Plan (PMP) is for the Phase III Communicator.
The project will deliver the Phase III Communicator hardware, software
and documentation for the Phase III Communicator. ODU is responsible for
the integration, acceptance, testing and training of the Total Computing
Environment.
1.1 Project Management Overview
back to top
Execution of the Project will be performed in accordance with the procedures
defined by the set of planning documents. These documents include Project
Management Plan*, System Quality Project Plan (SQPP), Software Management
Plan (SMP), Configuration Management Plan (CMP), Engineering Management
Plan (EMP), Manufacturing Plan (MP), and Risk Management Plan (RMP) (see
Figure 1). The responsibilities of the Project Team, the capabilities
of the system, and the Project deliverables are detailed under the contractual
provisions, as well as Phase III Communicator technical, management, and
cost proposals.
* This Project Management Plan shall be deemed to meet the contractual
requirement of a Project Management Plan.
click on the image for full size view
This Project Management Plan describes the management
philosophy, project organization, schedule, and major milestones that
serve as the guide for execution of the Project. The PMP also provides
the customer and the quality team with the information they need to monitor
and evaluate the progress of the effort. This plan provides the following
pertinent information:
• Corporate Organization
• Project Team Organization With Areas of Responsibility
• Work Breakdown Structure
• Project Planning
• Progress Reporting and Team Management
• Detailed Project Schedule and Milestones
• Project Reviews
The Project Management Plan provides guidance for the
content and execution of the following plans:
• Risk Management
• Engineering Management
• Software Management
• ILS Support
• Data Management
• Installation
• Configuration Management
• Acceptance Management
1.2 Corporate Structure
back to top
The entirety of ODU Corporation supports the Phase III Communicator Project.
In 2003, ODU made a commitment to incorporate new, innovative ideas using
COTS hardware and software. Over the past 5 years this commitment has
resulted in the development and installation of over 25 new and innovative
projects. All of these projects have complete prototypes, successfully
tested, and are in reasonable operation. The following is CS 410 and CS
411 Corporate organizational structure:
• CEO & President, Professor Brunelle Corporation.
• Group Vice President.
• Computer Science Project Office. CS 410 Project Office will execute
the project and provide day-to-day senior management supervision, management,
engineering, and administrative resources necessary to manage and administer
the Phase III Communicator Project.
1.3 Management Approach
back to top
Phase III Communicator’s management goal is to work closely with
the customer to fully understand the system requirements and field a system
that meets those requirements. The management approach to executing contracts
at ODU is based on the philosophy that successful Projects are delivered
by goal-oriented teams. A Project Manager (PM) will lead the Phase III
Communicator team. The PM is responsible for all planning, programmatic,
technical, and financial aspects of the Project. The PM is the primary
Point of Contact (POC) for the customer. The primary duties include supervision
of all planning, scheduling, financial and technical activities, and customer
liaison. The PM is responsible for all Project-related decisions and commitments
with approval, as required, from the Corporate Management Team.
A key element of ODU’s Project management approach is customer involvement.
ODU encourages the customer to retain an active role in monitoring the
progress of all aspects of the Project. The customer is encouraged to
discuss technical details directly with members of the Project team, provide
planning and schedule recommendations, and assist in resolution of technical
and programmatic issues. In order to facilitate customer involvement,
Phase III Communicator Project will provide access to project information
including, but not limited to:
• PROJECT Plans and Schedules
• PROJECT Status
• Earned Value
• Formal Review Material
• Action Items
• System Drawings and Documentation
1.4 Project Team back
to top
The Project Team is committed to provide the best value by delivering
COTS, open architecture, and low-risk systems at the lowest cost. This
commitment is attainable because it is based on the re-use of existing
technology that is field-proven. Through strategic teaming and an extensive
system selection process, ODU has assembled a cohesive Project Team that
is experienced with the implementation of each component that will comprise
the Phase III Communicator Computing Environment.
Project Manager. Overall management responsibility for Phase III Communicator
Project is assigned to a Project Manager who is responsible for planning
and coordination of the day-to-day technical, contractual, and financial
aspects of the project. He is responsible for the generation and management
of all project schedules, for the coordination of project staff assignments,
and for coordinating all project activities. His principal assistants
are:
• Technical Director. The TD provides overall technical direction
for the Project Team. He is the senior engineer and will directly oversee
production and integration to ensure that all-contractual requirements
are met. Several senior engineers in the areas of software design, development,
and production will assist the TD.
• System Engineering. The System Engineer is responsible for system-level
activities to ensure the system meets the specification requirements.
He is responsible for the development of the system specifications, system
design documents, interface documents, test plans, and procedures.
• System Development Engineer. The System Development Engineer is
responsible for the development of system software functions as defined
in the system specifications. He is responsible for integration of all
system components to meet the performance requirements of the system.
• Production. The Production Manager is responsible for all system
electronics hardware components, production, and test activities at ODU.
He will work with the System Engineering and Development Manager to ensure
production, testing, and installation schedules. The Production Manager
is assigned responsibility to provide technical oversight during client
installation phase, Set-to-Work, and formal testing. His primary responsibilities
include coordination of installation plans; managing the configuration,
developing system level installation documentation, and support of the
Integrated Logistics Support (ILS) Manager.
• ILS Manager. The ILS Manager is responsible for Integrated Logistics
Support (ILS) for the project and to collect and deliver the operator
manuals, system manuals, and training material.
• Contract Manager. The Contract Manager administers the contract
and is the primary point of contact between ODU and subcontractors for
contract matters. In addition to supporting the Project Manager, the CM
is responsible for coordinating all contractual aspects of the project,
including CDRL deliveries and milestone payments.
1.5 Project Duration back
to top
The Phase III Communicator Project is a four year project through delivery
of the first Unit. The Phase 0 schedule consists of a preliminary design
research and SBIR funding approval. Phase I is the prototype development,
completing a manual, and SBIR funding approval. Phase II is the preliminary
production and software development. Phase III is full production and
indoctrination course to first customers. Then the project switches to
out years where technical support and phone lines are in place.
Work Breakdown Structure
The project Work Breakdown Structure (WBS) reflects the budgeted cost
versus resources required to complete each task. The structure will follow
Handbook 881. The WBS phase numbers are integrated as part of the master
project schedule. Budgets for work planned are entered into ODU’s
financial tracking system for each WBS element, actual costs and estimates
to complete are managed by the Project Manager. The WBS element numbers
will be structured according to the Contract Statement of Work and will
be used to track project costs, progress, earned value and progress relative
to the master project schedule. The WBS management tools that ODU will
use are MICROFRAME 2.2 and Deltek V5.0.
2 PROJECT PLANNING back
to top
The Phase III Communicator Project team office will maintain the project
master schedule. The master schedule contains a line item for each WBS
element and will be used to track the progress of each element. All deviations
from the master schedule must be coordinated with the project office.
It is the responsibility of each team member to call attention to possible
schedule deviations at the earliest opportunity. The project office will
coordinate the project schedule with ODU. The project will be developed
in phases; within each phase, formal reviews will play an integral part
in monitoring project progress. All formal reviews will be announced four
weeks in advance of the starting date.
Phase III Communicator Project will take a “top down approach”
to the Project Schedule, meaning that we will pace our workload to fit
the overall Project requirements. Particular attention will be given to
timely milestone completions. It is recognized that the schedule is particularly
tight, containing critical project milestones during the first year, and
adequate personnel will be available in order to keep the project moving
forward.
3 PROGRESS PERFORMANCE ASSESSMENT
back to top
All Phase III Communicator team members will participate in progress reporting
and team management. ODU will track technical and financial progress of
the project. Reviews will be held monthly or as mutually agreeable between
the Phase III Communicator team and Professor Brunelle.
• Report on progress to date
• Present work to be performed during the next month
• Present status of all deliverables and review planned delivery
dates
• Present status of all received GFX/PFX items
• Plan and coordinate activities
• Discuss technical or programmatic issues as necessary.
In preparation for the meetings the Phase III Communicator Project Manager
will collect the current status data on relevant on-going activities,
progress against schedule and budget, and planned activity for the next
reporting period. Quality reviews of all project documentation and procedures
will be held periodically. In particular, the quality project will be
involved with project deliveries and milestones and will work off of the
master project schedule to plan project audits. Technical, financial and
quality progress, and status reporting will be conducted according to
the following general guidelines.
3.1 Technical Progress and Reporting
back to top
The schedule for the project is established during the planning phase
and monitored throughout the performance period. The schedule contains
an entry for each WBS element. The percentage of completion for each WBS
element is determined as necessary to manage project progress and is reviewed
at least quarterly during Professor Bunelle’s review.
3.2 Financial Management and Reporting
back to top
The financial profile for the Project is established during the planning
phase and monitored throughout the performance period. This profile is
generated by assigning accounting phase numbers to every Project activity
that has been identified as a scheduled event. A budget representing labor
costs, materials purchase, and other expenditures (such as travel expenses)
is then prepared for every phase. The schedule and budgets are then integrated
to provide a spending profile for the phase. The Project spending profile
represents a summary of phase spending profiles.
The PM provides an information package that identifies the phase numbers
assigned to each activity, the corresponding budgets and schedules, the
overall spending profile for the project, and a synopsis of all major
deliverables and milestones specified in the contract. The PM uses this
information, combined with an on line financial summary of the Project
to track its financial status on a weekly basis. An updated spending profile
is provided automatically by the Contracts Administrator on a monthly
basis, or upon request from the PM. The PM uses the financial summary
in conjunction with his assessments of technical progress to track the
overall status of the efforts.
3.3 Earned Value back
to top
Earned Value Ratios will be reported as required. At a minimum, Phase
III Communicator Project team will determine earned value quarterly at
the overall Project level and will report at the 2nd level of WBS indenture
in order to provide additional information.
Ratios will be reported in the form of the Schedule Performance Index
(SPI) and the Cost Performance Index (CPI). Ratios below 0.90 will be
explained in further detail.
SPI is to be calculated as follows:
SPI = BCWP (Budgeted Cost of Work Performed)
BCWS (Budgeted Cost of Work Scheduled)
CPI is to be calculated as follows:
CPI = BCWP (Budgeted Cost of Work Performed)
ACWP (Actual Cost of Work Performed)
ODU will use a combination of its Deltek Accounting and Microframe Project
Manager Software Projects in order to calculate the ratios. On a monthly
basis, actual costs will be downloaded into Microframe from Deltek. A
baseline of work to be performed will be established in Microframe and
will provide the BCWS. Milestones will be applied against the various
WBS elements, and % complete status of the milestones will be updated
on a monthly basis. Based upon % complete, Microframe will calculate BCWP,
or earned value, at the individual WBS level and determine the earned
value at the overall project level.
3.4 Quality Process and Reporting
back to top
Quality management on the project will be a team effort. The Quality System
Manager will coordinate conduct, quality reviews, and audits. The PM is
ultimately responsible for the development and implementation of the System
Quality Project Plan. The SQPP is an umbrella plan which incorporates
the quality projects of the project team members. The SQPP describes a
team quality concept, including Process Coordination and Quality Evaluators.
Team members are responsible for performing the processes required to
complete Project tasks. Quality Evaluators are responsible for verifying
that the development, production, and handling of all documentation, software,
and hardware are performed in accordance with the SQPP and its component
processes. The team is also responsible for conducting periodic reviews
and evaluations of work in process; attending in house test events, and
supporting in house Project reviews. All planned quality project activities
and quality evaluations (internal audits) are submitted to the PM for
review.
3.5 Monthly Progress Report
back to top
Phase III Communicator Project will submit a monthly progress reports.
The report shall cover, at a minimum, the following:
• Progress Summary;
• The Variance Statement;
• Critical Path Analysis;
• Milestone Deliverables, planned actual and forecast;
• Earned Value Schedule and Cost Performance Indices;
• Dependencies: a ‘critical items list’ of all items,
whether or not the Contractor’s direct responsibility, which could
jeopardize timely completion of the work or any significant parts of the
project;
• Risk Status: update of risk register;
• Look Ahead (Future action and Forecast);
• Resource Profile;
• Work Package/Activities planned, actual & forecast status;
• Milestone/Deliverables planned, actual & forecast status;
• Configuration Change Control issues;
• Quality Actions (Reviews, audits);
• One Page Plans and Reports summarising the above for inclusion
in the Purchaser’s monthly report; and
• Commercial: amendments to Contract status report; No later than
meeting + 10 working days.
4 REVIEWS back
to top
Reviews will play an integral part in the management and monitoring of
all phases of the Phase III Communicator Project. Informal reviews with
the Project team members will be held at all levels on a weekly basis
to ensure that the project stays on track. Formal technical reviews will
be held to ensure that the project is proceeding as planned. The types
of reviews, their purpose and presented information are addressed in the
following paragraphs.
4.1 Project Management Reviews
back to top
Project Management Reviews (PMRs) will be conducted with ODU and subcontract
representatives. The first PMR will be conducted in July 2004; thereafter
PMRs will be conducted approximately every six months (immediately preceding
each technical review). The PMRs are scheduled to discuss programmatic
issues related to the development and implementation of the Project. The
reviews will provide the opportunity to review the progress of the effort;
as well as to conduct milestone reviews of deliverables, and identifies
and resolves any issues that may arise during the execution of the tasking.
The PM will ensure that all project related information required to meet
the objectives of the review are prepared and delivered not later than
two weeks prior to the scheduled review date. The PM will also be responsible
for identifying the Phase III Communicator Project team personnel who
will attend the review. The PM will attend all Project Management Reviews.
The following information will be prepared in support of each PMR. Recorded
during the review and delivered before the completion of the review.
4.2 Technical Reviews
back to top
Formal technical reviews will be conducted on the dates specified in the
master schedule. The reviews will be held jointly with ODU, Phase III
Communicator Project team members and sub-suppliers as necessary. An agenda
and review material will be submitted to ODU two weeks prior to the scheduled
meeting. Review meeting minutes will be delivered before the completion
of the review. The objectives for each review are outlined below.
Reviews will be held to validate the direction taken for the design, development,
and test of the system. The System Requirements Review (SRR), Preliminary
Design Review (PDR), and Critical Design Review (CDR) will be formal reviews
held at ODU’s facility. The Test Readiness Reviews (TRR) will be
formal reviews held prior to HAT & SAT.
System Requirements Review is conducted to ensure that the Project team
fully understands the system performance requirements specified in the
System/Segment Specification. A detailed review of requirements for the
system and each subsystem will be reviewed. The System/Segment Specification
(Technical Specification) will be used in the review.
System Design Review is conducted to present and review the system design.
System requirement allocation to each system component will be discussed.
The general approach to be taken for the integration of each system component
will be presented. The documents listed below will be used in the review.
This will be an informal review. The data will be included in the PDR.
• System/Segment Design Document
• System Interface Design Document
Software Requirements Review is conducted to review the software specification
and interface requirement specifications. This review will be conducted
as part of the PDR.
Preliminary Design Review is conducted to present the preliminary design
of the Project System. The functional requirements of each subsystem will
be discussed in detail. The following documents will be used in the review:
Critical Design Review is conducted to review system integration issues.
In particular the review will focus on system interfaces in preparation
for Subsystem FAT.
Test Readiness Reviews are held to determine if the system is ready to
proceed to the next level of test. Test configurations and results from
the previous test efforts will be presented. The test report from the
previous test will be used in the review. The following TRRs will be performed:
• Prior to FAT
• Prior to HAT
• Prior to SAT
4.3 Quality Reviews
back to top
The PM supported by the quality system manager (QSM) will establish the
time and identify attendees for all formal reviews. He will also coordinate
with the appropriate managers to conduct quality reviews at key project
milestones, and in preparation for formal reviews with the customer. Informal
peer review and engineering planning meetings will also be held at the
discretion of each subsystem manager to discuss technical issues, conduct
internal comment reviews, and provide technical guidance to members of
the Project team. As part of the quality activities for the project, the
quality team will conduct informal reviews to:
• Evaluate the processes used by the Project team members to perform
project tasks;
• Evaluate deliverable products for compliance with contract requirements;
• Evaluate work-in-process during engineering reviews;
• Document results of each evaluation; and
• Recommend corrective and preventive actions if necessary.
|