ID | Task Name | Duration | Start | Finish |
1 | Research & Design | 48 days | Mon 10/1/01 | Wed 12/5/01 |
2 | Presentation II - Feasibility | 12 days | Mon 10/1/01 | Tue 10/16/01 |
3 | Presentation III - Milestones | 20 days | Wed 10/17/01 | Tue 11/13/01 |
4 | Functional Spec Rough Draft | 18 days | Wed 10/17/01 | Fri 11/9/01 |
5 | Project Description | 18 days | Wed 10/17/01 | Fri 11/9/01 |
6 | Implementation Plan | 18 days | Wed 10/17/01 | Fri 11/9/01 |
7 | Draft Budget | 18 days | Wed 10/17/01 | Fri 11/9/01 |
8 | Bibliography / Biography | 18 days | Wed 10/17/01 | Fri 11/9/01 |
9 | Abstract, TOC, Cover Page | 18 days | Wed 10/17/01 | Fri 11/9/01 |
10 | Presentation IV - Group Approval | 20 days | Wed 11/14/01 | Tue 12/11/01 |
11 | Functional Specifications | 37 days | Wed 10/17/01 | Thu 12/6/01 |
12 | Web Site | 49 days | Mon 10/1/01 | Thu 12/6/01 |
13 | Database Ready to Go | 85 days | Mon 10/1/01 | Fri 1/25/02 |
14 | Obtain Working Database | 49 days | Mon 10/1/01 | Thu 12/6/01 |
15 | Assess Necessary Fields | 1 day | Thu 12/6/01 | Thu 12/6/01 |
16 | Adapt Database to Fit Prototype | 10 days | Mon 1/14/02 | Fri 1/25/02 |
17 | Prototype Software Component | 64 days | Mon 1/28/02 | Thu 4/25/02 |
18 | Opening Presentation Screen | 11 days | Mon 1/28/02 | Mon 2/11/02 |
19 | Query / Search Capability | 26 days | Mon 1/28/02 | Mon 3/4/02 |
20 | Match Results Output | 20 days | Thu 2/28/02 | Wed 3/27/02 |
21 | Item Found Display | 20 days | Fri 3/29/02 | Thu 4/25/02 |
22 | Prototype Hardware Component | 21 days | Mon 1/28/02 | Mon 2/25/02 |
23 | Hardware Selected | 21 days | Mon 1/28/02 | Mon 2/25/02 |
24 | Prototype Simulation Testing | 9 days | Wed 4/24/02 | Mon 5/6/02 |
25 | Prototype Delivery / Detailed Product Specifications | 83 days | Mon 1/14/02 | Wed 5/8/02 |
26 | Funding / Project Acceptance | 29.5 days | Fri 4/26/02 | Thu 6/6/02 |
27 | Obtain Management Facilities | 11 days | Wed 5/29/02 | Wed 6/12/02 |
28 | Marketing | 47 days | Thu 6/6/02 | Fri 8/9/02 |
29 | Sales | 47 days | Thu 6/6/02 | Fri 8/9/02 |
30 | First Customer Contracts | 8 days | Mon 8/5/02 | Wed 8/14/02 |
31 | Production | 19 days | Fri 8/9/02 | Wed 9/4/02 |
32 | Training | 16 days | Thu 9/5/02 | Thu 9/26/02 |
33 | Production model / field testing | 12 days | Thu 9/26/02 | Fri 10/11/02 |
34 | Delivery & Distribution | 15 days | Fri 10/11/02 | Thu 10/31/02 |
35 | Full Scale Production and Sales | 500 days | Mon 11/4/02 | Fri 10/1/04 |
36 | Marketing | 500 days | Mon 11/4/02 | Fri 10/1/04 |
37 | Sales | 500 days | Mon 11/4/02 | Fri 10/1/04 |
38 | Manufacturing | 500 days | Mon 11/4/02 | Fri 10/1/04 |
39 | Legal | 500 days | Mon 11/4/02 | Fri 10/1/04 |
40 | Administration | 500 days | Mon 11/4/02 | Fri 10/1/04 |
|
|
|