Phase One (Feasibility, Six Months)
  Personnel Resources  
Positions   Number  Annual Salary Months Time %  Allotted Salary
Program Manager/Software Engineer 1  $      88,000.00 6 50.00%  $      22,000.00
Network Engineer   1  $      50,000.00 6 50.00%  $      12,500.00
Programmers   2  $      50,000.00 6 50.00%  $      25,000.00
Database Administrator 1  $      60,000.00 3 50.00%  $        7,500.00
Office Assistant   1  $      25,000.00 6 100.00%  $      12,500.00
  Personnel Total            $      79,500.00
  Hard Resources    
Catagory Item Qty  Cost Months    Allotted Budget
Office            
  10x10 sqft (Mgmt) 1  $           300.00 6    $        1,800.00
  20x20 sqft (Other) 1  $        1,000.00 6    $        6,000.00
Hardware            
  Workstations 3  $           749.00      $        2,247.00
  Color Printer 1  $           199.00      $           199.00
  B&W Printer 1  $             99.00      $             99.00
  CAD CPU 1  $           999.00      $           999.00
  CAD Table Unit 1  $           820.00      $           820.00
  CAD Staff Station 1  $        2,200.00      $        2,200.00
  CAD Printer 1  $           210.00      $           210.00
Software            
  Linux Pro 4  $           120.00      $           480.00
  Office Package 3  $           400.00      $        1,200.00
  Internet    $             40.00 6    $           240.00
  Other 1  $           670.00      $           670.00
Travel      $        1,500.00      $        1,500.00
Office Supplies      $        1,500.00      $        1,500.00
  Hard Resources Total            $      20,164.00
Total Phase One Cost            $      99,664.00