1 | Project Proposal Phase | Mon 9/3/01 | Tue 12/11/01 | 72 days | |
2 | Web Development | Wed 9/19/01 | Wed 12/5/01 | 56 days | Technical Operations |
3 | Web Information Page | Thu 12/6/01 | Thu 12/6/01 | 0 days | |
4 | Establish Financial Plan | Mon 9/3/01 | Fri 11/23/01 | 60 days | Finance Office |
5 | Establish Business Development Plan | Mon 9/3/01 | Fri 11/23/01 | 60 days | Business Development |
6 | Establish DORS Development Plan | Mon 9/3/01 | Fri 11/2/01 | 45 days | |
7 | Establish Engineering Process | Mon 9/3/01 | Fri 10/12/01 | 30 days | Technical Operations |
8 | Establish Engineering Controls | Mon 10/15/01 | Fri 11/2/01 | 15 days | Technical Operations |
9 | Develop Functional Decomposition | Mon 9/3/01 | Tue 12/11/01 | 72 days | |
10 | Survey Customer Base | Mon 9/3/01 | Wed 10/3/01 | 23 days | Business Development |
11 | Survey Stakeholders | Thu 10/4/01 | Fri 10/19/01 | 12 days | Business Development |
12 | Establish Objective | Mon 10/22/01 | Thu 10/25/01 | 4 days | Business Development |
13 | Define Scope | Fri 10/26/01 | Wed 10/31/01 | 4 days | Business Development |
14 | Establish Requirements | Thu 11/1/01 | Tue 11/20/01 | 14 days | Business Development |
15 | Establish Functions | Wed 11/21/01 | Mon 12/10/01 | 14 days | Technical Operations |
16 | Preliminary Functional Review | Mon 12/10/01 | Mon 12/10/01 | 0 days | |
17 | Refine Functional Specification | Tue 12/11/01 | Tue 12/11/01 | 1 day | Technical Operations |
18 | Critical Functional Review | Tue 12/11/01 | Tue 12/11/01 | 0 days | |
19 | Functional Specifications | Tue 12/11/01 | Tue 12/11/01 | 0 days | |
20 | Project Design Phase | Wed 12/12/01 | Thu 4/4/02 | 82 days | |
21 | Complete Increment Planning | Wed 12/12/01 | Wed 2/20/02 | 51 days | Technical Operations |
22 | Complete Staffing Plan | Wed 12/12/01 | Tue 3/26/02 | 75 days | |
23 | Organization Chart | Wed 12/12/01 | Mon 12/24/01 | 9 days | Program Management |
24 | Recruiting | Tue 12/25/01 | Wed 1/30/02 | 27 days | Business Development |
25 | Interview | Thu 1/31/02 | Tue 3/26/02 | 39 days | Program Management |
26 | Complete Trade Studies | Wed 12/12/01 | Tue 12/25/01 | 10 days | |
27 | Hardware | Wed 12/12/01 | Tue 12/25/01 | 10 days | Technical Operations |
28 | Software | Wed 12/12/01 | Tue 12/25/01 | 10 days | Technical Operations |
29 | Contractors | Wed 12/12/01 | Tue 12/25/01 | 10 days | Business Development |
30 | Derive Requirements | Wed 12/26/01 | Tue 2/5/02 | 30 days | Technical Operations |
31 | Preliminary Design Review | Tue 2/5/02 | Tue 2/5/02 | 0 days | |
32 | Refine Requirements | Wed 2/6/02 | Thu 2/21/02 | 12 days | Technical Operations |
33 | Establish Prototype | Fri 2/22/02 | Thu 4/4/02 | 30 days | Technical Operations |
34 | Critical Design Review | Thu 4/4/02 | Thu 4/4/02 | 0 days | |
35 | Project Implementation Phase | Fri 4/5/02 | Tue 5/20/03 | 292 days | |
36 | Purchase Office Space | Fri 4/5/02 | Thu 4/25/02 | 15 days | Finance |
37 | Hire Staff | Fri 4/26/02 | Thu 6/6/02 | 30 days | Business |
38 | Purchase Hardware/Software | Fri 6/7/02 | Wed 6/26/02 | 14 days | Finance |
39 | Install Hardware/Software | Thu 6/27/02 | Wed 7/24/02 | 20 days | Technical Operations |
40 | Establish Database | Thu 7/25/02 | Wed 8/7/02 | 10 days | Technical Operations |
41 | Established Webserver | Thu 8/8/02 | Mon 8/19/02 | 8 days | Technical Operations |
42 | Technical Review (Development Infrastructure) | Mon 8/19/02 | Mon 8/19/02 | 0 days | |
43 | Develop Front-end Templates | Tue 8/20/02 | Mon 12/2/02 | 75 days | Technical Operations |
44 | Technical Review (User Interface) | Mon 12/2/02 | Mon 12/2/02 | 0 days | |
45 | Develop Application Software | Tue 12/3/02 | Mon 2/24/03 | 60 days | Technical Operations |
46 | Technical Review (Application Software) | Mon 2/24/03 | Mon 2/24/03 | 0 days | |
47 | Test Requirements | Tue 2/25/03 | Thu 4/24/03 | 43 days | Integration & Test |
48 | Technical Review (Product Evaluation) | Thu 4/24/03 | Thu 4/24/03 | 0 days | |
49 | Establish Infrastructure | Fri 4/25/03 | Fri 5/16/03 | 16 days | Technical Operations |
50 | Technical Review (Product Acceptance) | Tue 5/20/03 | Tue 5/20/03 | 0 days | |
51 | Project Completion | Fri 5/30/03 | Fri 5/30/03 | 0 days | |