Work Breakdown Structure
> >

Project Definition & Planning: Phase I

  The first phase of the WSD project is dedicated largely to planning and research, and follows the CS410 course schedule and requirements closely. Early on, the project.s goals, objectives, target market, and possible risks will be defined. Based on these determinations, research will begin to prove the project.s feasibility. General internet research will answer many questions, but interviews and surveys will likely be needed to answer specific questions about technical feasibility or our target market. Finally, the plan that will be used to guide the project to success must be developed, including budget, Work Breakdown Structure, identified milestones, and schedules.

(Note: .Internal Personnel. references in the Resources listings refer to ODU students of Junior-level standing or higher in majors relevant to the area in question, usually Computer Science.)


Phase I Objectives

00000: Complete required planning for the WSD

  10000: Define the general scope of the WSD project.
    11000: Determine the project goals and objectives.
    12000: Determine the problem the project is going to solve.
  19999: Project scope defined and approved.

  20000: Prove the WSD project is feasible.
    21000: Determine and mitigate the risks to the project.
      21100: Identify the risks the project carries.
      21200: Determine mitigations for identified risks.
    22000: Prove viability of target market.
    23000: Determine existence of required technology.
    24000: Prove financial feasibility.
      24100: Estimate a cost per unit.
      24200: Determine purchasing power of target market.
      24300: Determine how many units must be sold to begin earning profit.
    25000: Present proof of feasibility to the review board.
      25100: Develop the feasibility presentation.
      25200: Give the feasibility presentation.
  29999: Feasibility proof accepted by review board.

  30000: Develop the detailed plan for the WSD project.
    31000: Determine the WSD project schedule.
      31100: Develop a list of project objectives by phase.
      31200: Determine tasks required for each objective.
      31300: Determine time required for each task.
      31400: Determine the project.s milestones.
    32000: Determine a preliminary WSD project budget.
      32100: Determine resources needed for each task.
      32200: Research cost of required resources.
    33000: Present detailed plan to the review board.
      33100: Refine and condense feasibility presentation.
      33200: Develop the milestone presentation.
      33300: Give the milestone presentation.
  39999: Detailed plan accepted by review board.

  40000: Prepare to seek final approval of the WSD project.
    41000: Fill in any gaps in the required information.
    42000: Refine and polish previously written documents.
    43000: Present all information to the review board.
      43100: Refine previous presentations.
      43200: Develop the approval presentation.
      43300: Give the approval presentation.
  49999: Approval granted by review board.

  50000: Procure SBIR funding for the WSD project
   51000: Develop Phase 1 (Feasibility) SBIR proposal.
   52000: Develop Phase 2 (Full R/R&D Effort) SBIR prposal.
  59999: MILESTONE: Funding for the WSD is secured.


Phase I Tasks

11001: Develop and research the project idea.
11002: Develop a set of goals, and objectives that must be met to reach them.
12001: Choose a preliminary problem area to investigate.
12002: Research and refine the problem area.

21101: Determine what risks the project faces.
21102: Research to determine ways to counter the identified risks.
22001: Construct and adminster a survey about our product.
22002: Determine a target market from the survey data.
23001: Research available technology to determine if it meets our needs.
23002: Research and determine if the technology and can be integrated together.
24101: Research the costs of the components for a unit.
24201: Determine from previous survey data how much our market will pay.
25101: Construct a slideshow presenting the feasibility proofs.
25102: Practice, review, and refine the presentation.
25201: Deliver the presentation before the review board.

31101: Develop a basic list of major objectives.
31102: Break each major objective down into smaller objectives.
31201: Determine what tasks must be completed to meet each objective.
31301: Research and determine standard time estimates for the tasks.
31302: Adjust estimates based on specifics of our project.
31401: Determine the major steps in completing the project.
31402: Identify a deliverable for each major step.
32101: Research to determine the general resources needed for each.
32102: Research to identify the best specific choices for each resource.
32201: Research the cost of the needed resources.
33101: Review comments on the feasibility presentation.
33102: Adjust, update, and correct the feasibility presentation.
33103: Condense the feasibility presentation for use in the milestone presentation.
33201: Construct a slideshow presenting the detailed plan.
33202: Practice, review, and refine the presentation.
33301: Deliver the presentation before the review board.

41001: Review SBIR requirements and project planning guidelines.
41002: Draft any missing documentation.
42001: Review previous documentation and criticisms/comments recieved.
42002: Make corrections and updates of those documents.
43101: Review comments on previous presentations.
43102: Adjust, update, and correct the previous presentations.
43103: Condense the previous presentations for use in the approval presentation.
43201: Construct a slideshow presenting the project.
43202: Practice, review, and refine the presentation.
43301: Deliver the presentation before the review board.

51001: Review requirements for Phase I SBIR
51002: Write and submit required documentation for Phase I SBIR
52001: Review requirements for Phase II SBIR
52002: Write and submit required documentation for Phase II SBIR


Phase I Required Resources

Management Requirements:
These are the managers. salaries for this phase. They are not tied to any
specific group of tasks, but are required nonetheless.

Management:
  General Manager (Mrs. Janet Brunelle)
    1 personnel at $7500/month, 2 months: $15,000
  Project Manager (Mark Kopmann)
    1 personnel at $6700/month, 2 months: $13,400
  Technical Writing Manager (Herbie Piland)
    1 personnel at $5400/month, 2 months: $10,800
  Project Webmaster & Promoter (Cort Tompkins)
    1 personnel at $4800/month, 2 months: $9,600
  Research Manager (Amine Benjelloun)
    1 personnel at $4200/month, 2 months: $8,400
  Design Manager (Okiima Pickett)
    1 personnel at $4200/month, 2 months: $8,400
  Funding Procurement Manager (Charles Edmunds)
    1 personnel at $4200/month, 2 months: $8,400
  Tech Manager (Chris Garrett)
    1 personnel at $5400/month, 2 months: $10,800
Total Cost: $84,800

10000s:
  Personnel
    Internal Personnel
      4 personnel at $15/hour, 5hrs each of 20 man/hours: $300
  Computer Equipment
    PCs (Hewlett Packard)
      $900/unit (HP Pavilion 530n+Monitor), 4 units: $3,600
    Internet Access (Exis.Net)
      $20/month/unit, 4 units: $80/month (1 month): $80
Total Cost: $3,980

20000s:
  Personnel
    Internal Personnel
      4 personnel at $15/hour, 30hrs each of 120 man/hours: $1,800
  Computer Equipment
    PCs (Hewlett Packard)
      HP Pavilion 530n+Monitor: (reused from 10000s)
    Software (Best Buy)
      $550/unit (Microsoft Office Pro XP), 1 unit: $550
    Internet Access (Exis.Net)
      Exis.Net: (reused from 10000s)
Total Cost: $2,350

30000s:
  Personnel
    Internal Personnel
      4 personnel at $15/hour, 60hrs each of 240 man/hours: $3,600
  Computer Equipment
    PCs (Hewlett Packard)
      HP Pavilion 530n+Monitor: (reused from 10000s)
    Software (Best Buy)
      Microsoft Office Pro XP: (reused from 10000s)
    Internet Access (Exis.Net)
      $20/month/unit, 4 units: $80/month (1 month): $80
Total Cost: $3,680

40000s:
  Personnel
    Internal Personnel
      4 personnel at $15/hour, 30hrs each of 120 man/hours: $1,800
  Computer Equipment
    PCs (Hewlett Packard)
      HP Pavilion 530n+Monitor: (reused from 10000s)
    Software (Best Buy)
      Microsoft Office Pro XP: (reused from 10000s)
    Internet Access (Exis.Net)
      $20/month/unit, 4 units: $80/month (1 month): $80
Total Cost: $1,880

50000s:
  Personnel
    Internal Personnel
      2 personnel at $15/hour, 18hrs each of 36 man/hours: $540
  Computer Equipment
    PCs (Hewlett Packard)
      $900/unit (HP Pavilion 530n+Monitor), 2 units: $1,800
    Software (Best Buy)
      $35/unit (Microsoft Works 7.0), 2 units: $70
    Internet Access (Exis.Net)
      $20/month/unit, 2 units: $40/month (5 months): $200
Total Cost: $2,610

PHASE I TOTAL COST: $99,400


Research & Development: Phase II

  Phase II is the meat of the project lifecycle of the WSD. It is here that the product itself is developed in detail, from the specifics of the hardware, to the user interface, and its outer appearance. Documentation is also constructed here, both that which will be included with the product itself, and repair manuals, legal documents such as copyrights, and funding applications. The CS411 coursework would also be completed within this period, both the documentation and prototype development components. Marketing, manufacturing, and supply contracts will be established during this time, as well as performing testing of the WSD.s components, both individually and integrated together in their final form.

(Note: .Internal Personnel. references in the Resources listings refer to ODU students of Junior-level standing or higher in majors relevant to the area in question, usually Computer Science.)


Phase II Objectives

00000: Complete the Wristband Sleep Detector (WSD)

  10000: Complete the hardware components of the WSD
    11000: Obtain subcontracters required to produce a hardware blueprint
    12000: Design the hardware blueprint for the WSD
      12100: Design the hardware blueprint for the watch component
      12200: Design the hardware blueprint for the heart monitor
      12300: Design the hardware blueprint for the alert functions
        12310: Design the hardware blueprint for the tone alarm
        12320: Design the hardware blueprint for the vibration alarm
      12400: Design the hardware blueprint for the wrist activity monitor
      12500: Design an integration plan for the hardware components
    13000: Select the best components required by the hardware blueprint
  19999: MILESTONE: Hardware design completed to specifications.

  20000: Complete the software components of the WSD
    21000: Choose from current personnel a group to design the WSD software
      21100: Choose personnel to design the internal software
      21200: Choose personnel to design the user-interface
    22000: Procure equipment required to develop all WSD software
    23000: Produce the software required for the WSD
      23100: Produce the software to run the watch component
      23200: Produce the software to run the heart monitor
      23300: Produce the software to run the alert functions
      23400: Produce the software to run the wrist activity monitor
      23500: Produce the software to run graphical user interface (GUI)
  29999: MILESTONE: WSD software completed to specifications.

  30000: Create an sleek and attractive look for the WSD
    31000: Obtain subcontracters required to produce the product.s design
    32000: Design the WSD.s appearance and look
    33000: Select the best components required by the design layout chosen
  39999: MILESTONE: Outward appearance design completed.

  40000: Complete all documentation required for the WSD
    41000: Complete the user documentation for the WSD
      41100: Choose personnel to write and maintain the user manual
      41200: Procure equipment required by the documentation personnel
      41300: Design simple to understand user documentation for the WSD
    42000: Complete the repair documentation for the WSD
      42100: Choose personnel to write and maintain the repair documentation
      42200: Procure equipment required by the documentation personnel
      42300: Design repair documentation for the WSD
    43000: Complete the management documentation for the WSD
      43100: Choose personnel to write and maintain the management documentation
      43200: Procure equipment required by the documentation personnel
      43300: Design and maintain management documentation for the WSD
    44000: Complete the CS411 course-required documentation
      44100: Choose personnel to write and maintain the CS411 documentation
      44200: Procure equipment required by the documentation personnel
      44300: Design and maintain management documentation for the WSD
    45000: Complete the legal documentation
      45100: Hire legal aid to write the legal documentation
      45200: Produce the disclaimer required by the WSD
      45300: Secure the copyrights and patents required by the WSD
  49999: MILESTONE: Documentation completed to specifications.

  50000: Complete testing of the WSD
    51000: Design a series of tests required to test the WSD
      51100: Confirm accuracy of the heart-rate monitor
         51110: Confirm its accuracy with reading heart-rate
         51120: Confirm its accuracy when calibrating itself to users
         51130: Confirm its accuracy when detecting sleep
      51200: Confirm accuracy of the wrist activity detector
         51210: Confirm its accuracy when detecting wrist movement/immobility
         51220: Confirm its accuracy when detecting sleep
      51300: Confirm effectiveness of .wake-up methods.
         51310: Confirm effectiveness of tone alarm
         51320: Confirm effectiveness of vibration alarm
      51400: Confirm accuracy and effectiveness of watch functions
      51500: Confirm effectiveness and user-friendliness of user interface
      51600: Confirm readability and usefulness of user documentation
    52000: Procure equipment required for all WSD product testing
  59999: MILESTONE: All testing completed: Product components work as required.

  60000: Develop the marketing strategy for the WSD.
    61000: Choose a retail chain to sell the WSD.
    62000: Supply the selected chain with WSD units.
  69999: MILESTONE: Sign a contract with a retail chain.

  70000: Develop a prototype of the WSD (CS411).
    71000: Choose personnel to design the prototype.
    72000: Choose a prototype design.
    73000: Procure required components for the prototype
    74000: Complete the WSD prototype.
  79999: MILESTONE: Prototype is complete and operational.


Phase II Tasks (ordered by group)

11001: Research existing manufacturing firms to determine the best choice
11002: Negotiate a contract for the required work with the selected firm
12101: Request multiple ideas for the watch component from the hired firm
12102: Choose the best idea in terms of quality vs. money
12201: Request multiple ideas for the heart monitor from the hired firm
12202: Choose the best idea in terms of quality vs. money
12311: Request multiple ideas for the tone alarm from the hired firm
12312: Choose the best idea in terms of quality vs. money
12321: Request multiple ideas for the vibration alarm from the hired firm
12322: Choose the best idea in terms of quality vs. money
12401: Request multiple ideas for the wrist activity monitor from the hired firm
12402: Choose the best idea in terms of quality vs. money
12501: Request integration of all required components
13001: Research the available components needed for the selected blueprints
13002: choose the best components in terms of quality vs. money

21101: Review skills and training of current staff
21102: Choose those best qualified to produce the internal software
21201: Review skills and training of current staff (can be done with 2110a)
21202: Choose those best qualified to produce the user-interface software
22001: Determine hardware, software, and other equipment required by the
software teams
22002: Research to determine the best value in terms of quality vs. cost
of what is needed
22003: Purchase the best versions of required equipment
23101: Create the software to run the watch component
23201: Create the software to run the heart monitor
23301: Create the software to run the alert functions
23401: Create the software to run the wrist activity monitor
23501: Create the software to run the graphical user-interface

31001: Research existing design firms to determine the best choice
31002: Negotiate a contract for the required work with the selected firm
32001: Request multiple designs from the hired firm
32002: Conduct a survey of our target market to determine the most
attractive design
33001: Research the available components needed for the attractive design
33002: Choose the best components in terms of quality vs. money

41101: Review skills and training of current staff (can be done with 2110a)
41102: Choose those best qualified to produce the user documentation
41201: Determine hardware, software, and other equipment required by the
writer team
41202: Research to determine the best value in terms of quality vs. cost
of what is needed
41203: Purchase the best versions of required equipment
41301: Write and maintain the user documentation for the WSD
42101: Review skills and training of current staff (can be done with 2110a)
42102: Choose those best qualified to produce the repair documentation
42201: Determine hardware, software, and other equipment required by the
writer team
42202: Research to determine the best value in terms of quality vs. cost
of what is needed
42203: Purchase the best versions of required equipment
42301: Write and maintain the repair documentation for the WSD
43101: Review skills and training of current staff (can be done with 2110a)
43102: Choose those best qualified to produce the management documentation
43201: Determine hardware, software, and other equipment required by the
writer team
43202: Research to determine the best value in terms of quality vs. cost
of what is needed
43203: Purchase the best versions of required equipment
43301: Write and maintain the management documentation for the WSD
44101: Review skills and training of current staff (can be done with 2110a)
44102: Choose those best qualified to produce the CS411 documentation
44201: Determine hardware, software, and other equipment required by the
writer team
44202: Research to determine the best value in terms of quality vs. cost
of what is needed
44203: Purchase the best versions of required equipment
44301: Write and maintain the CS410 documentation for the WSD
45101: Research law firms and determine the best choice
45102: Hire lawyers from that firm to aid us with legal documentation
45201: Determine what health/safety risks, if any, our product poses
45202: Draft a disclaimer that speaks to those risks
45301: Determine what parts of our product should be copyrighted/patented
45302: Secure all required copyrights and patents

51111: Conduct a test comparing our heart-rate monitor to proven heart-
rate monitors
51112: Redesign our components and repeat testing if necessary
51121: Conduct tests to determine if the heart-rate monitor calibrates
properly
51122: Redesign our components and repeat testing if necessary
51131: Conduct tests to determine if/how/when the heart-rate monitor detects
sleepiness
51132: Redesign our components and repeat testing if necessary
51211: Conduct tests to determine if/how/when our product detects wrist
activity
51212: Redesign our components and repeat testing if necessary
51221: Conduct tests to determine if/how/when the wrist activity monitor detects
sleepiness
51222: Redesign our components and repeat testing if necessary
51311: Conduct a test to determine if the tone is successful at alerting
people
51312: Redesign our components and repeat testing if necessary
51321: Conduct a test to determine if the tone is successful at alerting
people
51401: Conduct tests of our product.s watch functions
51402: Redesign our components and repeat testing if necessary
51501: Conduct tests to see how easily people learn and use the GUI
51502: Redesign our components and repeat testing if necessary
51601: Conduct tests to see how readily people understand the user
documentation
51602: Redesign our documentation and repeat testing if necessary
52001: Determine hardware, software, and other required for all product
testing
52002: Research to determine the best value in terms of quality vs. cost
of what is needed
52003: Purchase the best versions of the required equipment

61001: Research retail chains to find the one best suited to sell our product
61002: Hire lawyers (4510) to negotiate a contract with the selected retail chain
62001: Produce the agreed upon number of units
62002: Deliver the agreed upon number of units to the chain.s outlets

71001: Review skills and training of current staff (can be done with 2110a)
71002: Choose those best qualified to produce the user documentation
72001: Determine an effective prototype design.
73001: Purchase components required by the design.
74001: Build the prototype according to the design.


Phase II Required Resources

Management Requirements:
These are the managers. salaries for this phase. They are not tied to any
specific group of tasks, but are required nonetheless.

Management:
  General Manager (Mrs. Janet Brunelle)
    1 personnel at $7500/month, 11 months: $82,500
  Project Manager (Mark Kopmann)
    1 personnel at $6700/month, 11 months: $73,700
  Technical Writing Manager (Herbie Piland)
    1 personnel at $5400/month, 11 months: $59,400
  Project Webmaster & Promoter (Cort Tompkins)
    1 personnel at $4800/month, 11 months: $52,800
  Research Manager (Amine Benjelloun)
    1 personnel at $4200/month, 11 months: $46,200
  Design Manager (Okiima Pickett)
    1 personnel at $4200/month, 11 months: $46,200
  Funding Procurement Manager (Charles Edmunds)
    1 personnel at $4200/month, 11 months: $46,200
  Tech Manager (Chris Garrett)
    1 personnel at $5400/month, 11 months: $59,400
Total Cost: $466,400


10000s:
  Subcontracts
    Choi Design Inc. ($250,000 contract)
  Personnel (Setting up the Partnership)
    Internal Personnel
      2 personnel at $15/hour, 30hrs each of 60 man/hours: $900
    Legal Aid
      1 lawyer at $300/hour, 25 man/hours: $7,500
    Overhead
      Overhead (40% on outside personnel): $3,000
Total Cost: $261,400

20000s:
  Subcontracts
    Choi Design Inc. (continued from 1000s)
  Personnel
    Technical Personnel
      3 programmers at $21/hour, 480hrs each of 1440 man/hours: $30,240
      1 software engineer at $30/hour, 480 man/hours: $14,400
    Overhead
      Overhead (40% on outside personnel) : $17,800
  Computer Equipment
    Bio-Feedback Device (J&J Engineering)
      $2,000/unit (C2-GP), 1 unit: $2,000
    Development Workstations
      $2,000/unit, 5 units: $10,000
Total Cost: $74,440

30000s:
  Subcontracts
    Choi Design Inc. (continued from 1000s)
Total Cost: $0 (paid for in 1000s)

40000s:
  Personnel
    Internal Personnel
      4 personnel at $15/hour, 40hrs each of 160 man/hours: $2,400
    Legal Aid
      1 lawyer at $300/hour, 15 man/hours: $4,500
    Overhead
      Overhead (40% on outside personnel): $1,800
  Computer Equipment
    PCs (Hewlett Packard)
      $900/unit (HP Pavilion 530n+Monitor), 4 units: $3,600
    Software (Best Buy)
      $35/unit (Microsoft Works 7.0), 4 units: $140
    Internet Access (Exis.Net)
      $20/month/unit, 4 units: $80/month (8 months): $640
Total Cost: $13,080

50000s:
  Personnel
    Internal Personnel
      4 personnel at $15/hour, 135hrs each of 540 man/hours: $8,100
    .Guinea Pigs. (Testers)
      25 personnel at $150 each: $3,750
    Overhead
      Overhead (40% on outside personnel): $1,500
  Supplies
    Heart Rate Monitor Baseline (JFM Inc.)
      $55/unit, 5 units: $275
    Motion Sensor Baseline (Metamotion Inc.)
      $5,000/unit, 1 unit: $5,000
    .Disposable. WSDs
      $60/unit, 20 units: $1,200
  Computer Equipment
    PCs (Hewlett Packard)
      $900/unit (HP Pavilion 530n+Monitor), 5 units: $4,500
    Software (CompUSA)
      Approx. $500/unit, 5 units: $2,500
Total Cost: $26,825

60000s:
  Personnel
    Internal Personnel
      1 personnel at $15/hour, 10 man/hours: $150
    Legal Aid
      1 lawyer at $300/hour, 20 man/hours: $6,000
    Overhead
      Overhead (40% on outside personnel): $2,400
  Computer Equipment
    PCs (Hewlett Packard)
      $900/unit (HP Pavilion 530n+Monitor), 1 unit: $900
    Software (Best Buy)
      $35/unit (Microsoft Works 7.0), 1 unit: $35
    Internet Access (Exis.Net)
      $20/month/unit, 1 unit: $20/month (2 months): $40
Total Cost: $9,525

70000s:
  Personnel
    Internal Personnel
      4 personnel at $15/hour, 18hrs each of 72 man/hours: $1,080
  Supplies
    Technical Components (Full Field Industrial Ltd.)
      $65.00/unit, 1 unit: $65
    Watchbands (Wing Fat Watch Bands Co.)
      $5.00/unit, 1 unit: $5
Total Cost: $1,150

PHASE II TOTAL COST: $852,820


Production & Outyears: Phase III

The final phase will see some of the WSD development team assigned to new projects. Revenue permitting will see the bulk of the team working on enhancements to the first release such as possibly a shock feature for enhanced alerting, creation of an interface to a virtual workstation, coordinating the research and subsequent results to improve upon reliability and expanded roles for the product such as dependable and accurate alerting in dangerous situations. The current project manager or one appointed will spearhead the effort to keep the WSD product alive and profitable.

It should be noted that many of the costs here, particularly annual costs, are estimates for the first year only. Costs beyond this period will be determined largely by performance of our product in the marketplace. Estimates for future periods should be determinable when this sales and market data becomes available. Our tentative post first-year plans are to dedicate 10% of our revenue to marketing (30000s) and 15% to continued research and development (40000s).

(Note: .Internal Personnel. references in the Resources listings refer to ODU students of Junior-level standing or higher in majors relevant to the area in question, usually Computer Science.)


Phase III Objectives

00000: Continue production and support of the WSD.

  10000: Produce WSD units ordered by our chosen retail chain.
  19999: MILESTONE: First order filled successfully.

  20000: Create and maintain a product support/repair center.
    21000: Establish a customer service department.
    22000: Establish a repair department.
  29999: MILESTONE: Support/Repair center established.

  30000: Continue to develop and improved the WSD.
    31000: Correct any weaknesses in the WSD design.
    32000: Improve on the current WSD design.
      32100: Identify new features desired by customers.
      32200: Review cost/benefit of adding new features.
  39999: MILESTONE: Continued R&D center established.

  40000: Continue marketing the WSD.
    41000: Maintain relations with our retail chain.
    42000: Explore further marketing options.
  49999: MILESTONE: Cusomter relations center established.
  

Phase III Tasks (ordered by groups)

10001: Determine with retailer.s sale data how many units to make.
10002: Request the units. production from our manufacturers.

21001: Develop a customer service algorithm.
21002: Hire an initial customer service staff.
22001: Purchase basic tools necessary for repairs.
22002: Hire repair engineers for the initial repair center.

31001: Review repair center data for trends.
31002: Investigate any trends found for design flaws.
31003: Repair any design flaws found in the review.
32101: Use a .rebate survey. to determine desired new features.
32102: Research feasibility of desired features.
32103: Develop new features if they are feasible.

41001: Review retail sales peformance with our chosen retailer.
41002: Renew our sales contract with the retailer.
42001: Explore the possibility of sales abroad through surveys.
42002: Develop marketing plans to take advantage of these possibilities.


Phase III Required Resources

Management Requirements:
These are the managers. salaries for this phase. They are not tied to any
specific group of tasks, but are required nonetheless.

Management:
  General Manager (Mrs. Janet Brunelle)
    1 personnel at $7500/month, 12 months/year: $90,000
  Project Manager (Mark Kopmann)
    1 personnel at $6700/month, 12 months/year: $80,400
  Technical Writing Manager (Herbie Piland)
    1 personnel at $5400/month, 12 months/year: $64,800
  Project Webmaster & Promoter (Cort Tompkins)
    1 personnel at $4800/month, 12 months/year: $57,600
  Research Manager (Amine Benjelloun)
    1 personnel at $4200/month, 12 months/year: $50,400
  Design Manager (Okiima Pickett)
    1 personnel at $4200/month, 12 months/year: $50,400
  Funding Procurement Manager (Charles Edmunds)
    1 personnel at $4200/month, 12 months/year: $50,400
  Tech Manager (Chris Garrett)
    1 personnel at $5400/month, 12 months/year: $64,800
Total Cost: $508,800 (per year)


10000s:
  Supplies (purchased every 25,000 units)
    Technical Components (Full Field Industrial Ltd.)
      $48.00/unit, 25,000 units: $1,200,000
    Watchbands (Wing Fat Watch Bands Co.)
      $4.75/unit, 25,000 units: $118,750
    Package Watches (Chong Ngai Packing Industrial Co.)
      $1.35/unit, 25,000 units: $33,750
Total Cost: $1,352,500 (per 25,000 units)

20000s:
  Personnel
    Customer Service
      2 personnel at $12/hour, 750hrs each of 1500 man/hours per year: $18,000
    Repair Staff
      1 personnel at $20/hour, 375hrs each of 750 man/hours per year: $7,500
    Overhead
      Overhead (40% on outside personnel): $10,200
  Supplies
    Note
      Parts for repairs will be purchased with each bulk order of complete
      units so that the 25,000+ unit discount may be taken advantage of. For
      the first order, we will purchase an extra 2% (500 units worth) of
      supplies. Future amounts will be determined on statistical analysis of
      previous repair needs.
    Technical Components (Full Field Industrial Ltd.)
      $48.00/unit, 500 units: $24,000
    Watchbands (Wing Fat Watch Bands Co.)
      $4.75/unit, 500 units: $2,375
    Package Watches (Chong Ngai Packing Industrial Co.)
      $1.35/unit, 500 units: $675
  Computer Equipment
    PCs (Hewlett Packard)
      $900/unit (HP Pavilion 530n+Monitor), 3 units: $2,700
    Internet Access (Exis.Net)
      $20/month/unit, 3 units: $60/month (12 months per year): $720
Total Cost: $2,700 (initial), $35,420 (per year), $20,050 (per 25,000 units)

30000s:
  Subcontracts
    Choi Design Inc. ($50,000/year contract)
  Personnel (Setting up the Partnership)
    Internal Personnel
      2 personnel at $15/hour, 375hrs each of 750 man/hours per year: $11,250
  Computer Equipment
    PCs (Hewlett Packard)
      $900/unit (HP Pavilion 530n+Monitor), 2 units: $1,800
    Internet Access (Exis.Net)
      $20/month/unit, 2 units: $40/month (12 months per year): $480
Total Cost: $1,800 (initial), $61,730 (per year)

40000s:
  Personnel
    Internal Personnel
      2 personnel at $15/hour, 375hrs each of 750 man/hours per year: $11,250
    Legal Aid
      1 personnel at $300/hour, 20 man/hours per year: $6,000
    Overhead
      Overhead (40% on outside personnel): $2,400
  Computer Equipment
    PCs (Hewlett Packard)
      $900/unit (HP Pavilion 530n+Monitor), 2 units: $1,800
    Internet Access (Exis.Net)
      $20/month/unit, 2 units: $40/month (12 months per year): $480
  Travel Budget
    Airline Tickets (PriceLine.com)
      Average of $250/ticket, 24 tickets per year: $6,000
    Hotel Rooms (PriceLine.com)
      Average of $120/night, 36 nights per year: $4,320
    Rental Cars (PriceLine.com)
      Average of $40/day, 36 days per year: $1,440
Total Cost: $1,800 (initial) $31,890 (per year)


TOTAL PHASE III Cost: $6,300 (initial), $638,840 (per year), $1,372,550 (per 25,000 units)


SBIR Submission / Project Plan
Final Approval Presentation
Milestones Presentation
Feasibility Presentation
The Survey
Market Analysis

Interview w/ Dr. Catesby Ware
National Commission on Sleep Disorder
More references...
Doze Driver Sleep Alarm
Sonic Nap Alert System
NapZapper
Personal Alarm System

Old Dominion University CS410
Computer Productivity Initiative, Fall 2002